Japan Offshore Wind Project Selection Criteria: Scoring System

Japan Offshore Wind Project Selection Criteria

Japan’s offshore wind sector is evolving rapidly, with strict selection criteria for project developers to ensure efficiency, sustainability, and economic benefits. This post breaks down the evaluation process for selecting offshore wind project operators under Japan’s regulatory framework.

Key Evaluation Criteria for Offshore Wind Project Selection

Japan’s offshore wind project selection process scores applications on a 240-point scale, focusing on two main factors:
1️⃣ Supply Price (120 points) – Lowest electricity price per kWh.
2️⃣ Project Feasibility (120 points) – Developer capability, financial stability, risk management, and local economic impact.

Scoring System Table_240 points scale
Graph_Scoring System_Japan offshore wind project

Supply Price 120pt

In Japan’s offshore wind project selection process, supply price (bid price per kWh) plays a crucial role. Developers are awarded up to 120 points based on their bid price, with lower prices receiving higher scores.

Supply Price Scoring System

The supply price score is calculated using the following formula:

Supply Price Score = (Lowest Bid Price) / (Bid Price Submitted by the Developer) × 120

✅ The lowest bid price among all bidders in the same offshore wind auction area is used as the reference.
✅ If a developer submits a price at or below the Zero Premium Level (ZPL), they automatically receive the full 120 points.

Key Rules for Supply Price Evaluation

(1) If the Lowest Bid Price is Above ZPL:

  • The lowest price in the auction determines the reference price for scoring.
  • Higher bid prices result in lower scores.

Example: Scoring Based on Supply Price (Above ZPL)

Developer Bid Price (JPY/kWh) Score Calculation Final Score
Company A (Lowest Price) 4.0 (4.0 / 4.0) × 120 120
Company B 4.5 (4.0 / 4.5) × 120 106.7
Company C 5.0 (4.0 / 5.0) × 120 96.0

(2) If the Lowest Bid Price is Below ZPL

  • If any developer submits a price below ZPL (3 JPY/kWh in this auction), all scores will be calculated using ZPL as the reference price instead of the lowest bid price.
  • Developers bidding at or below ZPL automatically receive 120 points.

 Example: Scoring Based on Supply Price (Below ZPL)

DeveloperBid Price (JPY/kWh)Score CalculationFinal Score
Company A (Below ZPL)2.8Automatic120
Company B (ZPL Level)3.0Automatic120
Company C3.5(3.0 / 3.5) × 120102.8
Company D4.0(3.0 / 4.0) × 12090.0

 

Project Feasibility 120pt

The specific method for confirming each item regarding project feasibility is as follows.

Project feasibility evaluation method
Project feasibility evaluation method r1 250129
Updated by METI Jan. 2025

Project Feasibility Scoring System

1️⃣ Five-tier grading system:
Projects are assessed using five rating levels plus a disqualification category:

  • Top Runner (100%)
  • Excellent (75%)
  • Middle Runner (50%)
  • Good (25%)
  • Minimum Required Level (0%)
  • Disqualified

2️⃣ Scoring distribution:
Each evaluation item is scored based on the highest-rated project in the same offshore wind auction area.

3️⃣ Speed of project implementation:
This is evaluated separately based on predefined criteria.

4️⃣ Final Feasibility Score Calculation:

Based on the total score of each evaluation item, the business feasibility evaluation score is calculated using the following formula.

Feasibility Score = (Bidder’s Score) / (Highest Score in the Auction Area) × 120 [full marks]

✅ The highest-scoring bidder in the auction area is used as the reference point (120 points).

Speed of implementation Scoring System

✅ The base date will be approximately 6 years, which is the average period until the start of operations for all participants in the second public offering, and the maximum score (20 pt) will be 5 years and 6 months, which takes into account further ingenuity by operators (6 months).
✅ Regarding the width of the steps (period) and the point difference for each step, 2 points will be deducted every 6 months.

Speed of implementation scoring system